  1. Open the left navigation menu using the hamburger icon
  2. Click Setup 
  3. Click Data Import 
  4. Right-click the PMSX_SEGMENT that matches your segment type - Parking Lot or Roadway
  5. Select Edit ConfigImage Removed
  6. In the pop-up window, use Edit Files button to upload the shape file that matches the data structure from Roadway Segment Import Configuration
  7. Click Select Source to select the file that was just uploaded
  8. Click Import to run the import.
  9. When the import has finished, click the Import Log tab to view the results

...

  1. Open the left navigation menu using the hamburger icon
  2. Click Setup 
  3. Click Data Import 
  4. Right-click the PMSX_CONDITION_SURVEY Import - Parking Lot or Roadway, depending on data,and select Edit Config.
    Image Removed
  5. In the pop-up window, use Edit Files button to upload the file that matches the data structure from Pavement Condition Data Configuration.
  6. Click Select Source button to select the file that was just uploaded.
  7. If you haven't imported the new condition data yet, select Append radio button under Import Method:
    Image Removed
    If you have already imported this year's condition data and want to re-upload a new batch of file it, select Replace radio button under Import Method, and update the Replace Where Clause:.Image Removed
  8. Click Import to run the import.
  9. When the import has finished, click the Import Log tab to view the results.

...

  1. Open the left navigation menu using the hamburger icon
  2. Click Asset Performance
  3. Click Calculated PCI
  4. In the Inspection pane in the top left, right-click and select Insert to insert a new inspection and fill in the Year that matches to the data year in the imported condition data. Then click Save.
    Image Removed
  5. Click the waffle icon Image Removed to open the module menu and select System. Select Tools > System Job > Schedules.
  6. In the Schedules window, select Pavement Express: Build Inspection Table from Condition Survey system job.
  7. In the Executables pane to the right, right-click the Calculate Pavement Inspection Table based on Condition Survey results executable, and select Define Argument(s). In the pop-up window, select the Inspection that was just created. Click OK.
    Image Removed
  8. Right click the Pavement Express: Build Inspection Table from Condition Survey system job, and select Rub Job. Wait for the job to finish. Text in pop-up window will conclude "...is done." Then click Close.
  9. Next, select Pavement Express: Calculate Pavement Condition Index (PCI) in Inspection Table system job. In the right pane, right-click the Calculate Pavement Condition Index (PCI) from Inspection Data executable, and select Define Argument(s). In the pop-up window, select the Inspection that was just created. Click OK.
  10. Right-click the Pavement Express: Calculate Pavement Condition Index (PCI) in Inspection Table system job, and select Rub Job. Wait for the job to finish. Text in pop-up window will conclude "...is done." Then click Close.
  11. The Pavement Condition Index (PCI) column in Pavement Condition Survey window is now calculated.

...