To create a work order from an Annual Work Plan or a Contract plan, use the following steps:
In the Approved Plan Items pane, locate the activity for which you will create a work order. Right-click the desired activity and select Issue Work. A dialog box is displayed. The left side of this dialog box lists the attributes needed to create a work order. The right side of the dialog box lists what can be chosen for the attribute selected on the left. When this dialog box is first displayed, the attribute at the top is selected.
Note: Since the asset type and activity are specified for the plan item from which work is being issued, the fields in the dialog box for these attributes are automatically completed by the system. |
In the row showing the new work order in the Work Orders pane, enter information in the columns with white backgrounds if you know this information.
Note: You must enter the amount of work to be done based on the activity unit in the Plan Amount column to activate the work order. |
Click . The work order is now created but is pending.
Note: When a work order is created, the application uses the calendar assigned to the work order (which is set up in the Custom Calendar window) to determine the days worked, but uses the hours an employee can work (as specified in the Employee window) to determine the number of hours that the employee works on each day. Therefore, the hours per day specified by the type of calendar should match the hours an employee works to avoid scheduling problems. For example, say you selected a 4 x 10 calendar (four days, 10 hours a day) and the employee is configured to work only 8 hours per day. Now if you create a work order that will take 40 hours, the application will set the duration of this work order to four days. However, the employee will be scheduled to only work 8 hours per day, leaving a deficit of 8 hours to complete the work order. To avoid this problem, set the employee to work 10-hour days in the Employee window. |