The Plan Matrix window provides two fields to select a plan and the following panes:

Note: After selecting a fiscal year and/or plan, click theĀ  icon to display information for the year and plan.

Plan Pane Description

The upper pane of the Plan Matrix window shows the activities for the fiscal year and plan selected at the top of the window. .

Note: The system will only display records where the administrative unit of the record is the same as the administrative unit you selected when you logged on. This is always true and not dependent on the state of the Access Regulated check box found in the User Control Properties dialog box.

Columns in the Plan Pane

The following columns are available (note that depending on the approach to planning taken, some of these columns can be hidden as described here):

Note: The format for this column and the month columns must be the same. AgileAssets recommends that all columns be formatted as integers. If you elect to format them as real numbers, each column must have the exact same number of digits to the right of the decimal place.
Note: If the activity's Performance Guideline does not include a value for the Unit Cost column, the value for the Amount column cannot be calculated and so the column will be blank. You cannot enter a value for the Amount column and have it saved by the system. Instead, to derive a value for the Amount column, you must add a value for the Unit Cost column to the activity's Performance Guideline, save the new value, and then run the Save Quantity Guidelines system job.
Note: The format for these columns and the Total Person Day column must be the same. AgileAssets recommends that all columns be formatted as integers. If you elect to format them as real numbers, each column must have the exact same number of digits to the right of the decimal place.
Note: The measurement unit may be person-hours or FTEs instead of person-days. This is configured at implementation by the setting of the WINDOW_PARAMS value for the Plan Matrix window (1 = FTEs; 2 = Person-hours; 3 = Person-days [default]).
Note: Assigning an integer value to this column necessarily causes the value in the Activity Totals column to be fixed. The value will not be altered during the leveling process. Hence, if the total number of person-days for activities assigned a priority value is greater than the total number of available person-days for the entire year, then the system will display an error message saying, "Required activities cannot be performed within available men days." You must either increase the total number of available person-days or remove priority values from some activities to recover from this error.
Note: Provided a value is given in the Rate column, you can calculate a value for this column by entering a value in the Amount column.

Description of the Right-click Shortcut Menu Commands

When you right-click a line item (or a group of selected line items), the system displays a shortcut menu. This menu contains the common commands along with the following special commands:

  1. For all records in the selected Plan/Year with a positive backlog, the difference (Total Cost minus Cost Man Days) will be entered in the Total Cost column for the current Plan/Year.
  2. Enters in the Total Per Days column of the current Plan/Year the backlog value from the source Plan/Year for all records with a positive backlog amount.
  3. Distributes the Total per Days quantity across all months according to the stored Performance Guidelines calendar.

When you execute this command, the application automatically refreshes the current Plan/Year to display all activities from the selected Plan/Year which had a positive backlog value. After reviewing the results of the move, and provided you are satisfied with the results, click the icon to keep the changes.

The results of the calculation replaces the current values.
If no information is provided in the Performance Guidelines window, then distribution is uniform (1/12th per month).
If the Performance Guideline does not include a rate, then the operation fails with an error message. This rate comes from the stored Performance Guideline for the year selected at the top of the window; see the note in Plan Matrix for more information.

Calendar Pane Description

The lower pane compares the planned resource allocations versus what is actually available. The Planned row shows the total planned person-days across all activities for each of the months. In this row, the columns are defined as follows:

The Available row shows the converted available person-days using the FTE number set for the month in the Owner Month FTE window and the budget value set in the Owner Year Budget window. In this row, the columns are defined as follows:

The Difference row shows the difference between the values in the columns of the Planned row and the columns of the Available row.

Note: The format for the month columns and the FTE/Year column must be the same. AgileAssets recommends that all columns be formatted as integers. If you elect to format them as real numbers, each column must have the exact same number of digits to the right of the decimal place.